Harbour Purpose of Funding Funding 2012 
Baltimore &   SkibbereenWestern Pier final account €39,000RoRo Slipway final account €21,000

North Pier extension final account €25,000

North Pier Phase 1 final works and account €150,000

North Pier Phase 2 works underway €745,000

Sailing Club Slipway completion of works €35,000

Proposed Inner Harbour Pontoon €70,000

Breakwater Design completion €30,000

Foreshore Licence Fees €135,000

€1,250,000
KinsaleCommercial Town Pier contract retention €30,000Adam’s Quay completion of work on site €555,000

Lobster Quay works completion €90,000

Fisherman’s Pontoon Remedial Works €140,000

Commercial Pier extension  Phase 1 €435,000

€1,250,000
Bantry BaySailing Club Pontoon €70,000Pier Derrick €70,000€   140,000